The work is carried out on behalf of the State Commission On Operation And Maintenance Of Tigris River Basin Projects

The work includes linking the fourth pumping station with the fifth pumping station of the Dabouni project in Wasit Governorate with a ductile pipeline instead of the old line. Spreading sand at the bottom of the pipe with an amount of (7000) m3 and burying it with soft soil with an amount of (61600) m3.

The cost of the work is (163,998,3000) dinars, and the implementation period is (250) days.

 