The work includes the implementation of a main channel in the form of (U-shape) and the secondary and distributed channels with its facilities of chest pacemakers, incisive pacemakers, tail passages, the origin of a waterfall and iron pedestrian bridges, in addition to the implementation of a puncture network of sub, secondary and combined tampons with its facilities from the mouths of the secondary and combined tampons, tubular bridges and the intersections of the trocars with Roads and temporary irrigation works to serve a total area of about (12,000) dunums, with a total amount of (14,667,416,750) dinars, and an implementation period of (850) days.