Contract (4600039760) / 2020

The work is carried out on behalf of ENI BV Iraq

It includes the design, preparation and construction of a filtration plant with a capacity of (300,000) barrels / day, in addition to operating and maintaining it for a per

 

Oil in water < 5ppm
Total suspended solids content ≤ 2 mg /l
Dissolved Oxygen content ≤ 50 ppb
Maximum particle size ≤ 4µm
Sulphate (SO4) max concentration 1000 mg /l

 

 The station consists of the following parts:

1-The intake basin at the general estuary.

2-A pumping station on the intake basin with a discharge of (3) m3/sec.

3- A station for filtering the water of the general estuary according to the above specifications.

4-Equipping the snail removal system in front of the filtering station.

5- (GRP) pipeline, with a length of (23) km In order to connect with injection stations.

6- A distribution lock station to regulate the distribution of water between the oil fields.

7-Equipping a dredger to maintain the general downstream section near the outlet.

8-Supplying and installing treated water tanks with a capacity of (13,200) m3

 

 

 

 

 

 

 

 

 

 

 

 

 

The cost of implementing the project, with a total amount of (285,500,000) dollars.

 