The work is carried out for the State Commission Of Dams and Reservoirs
It includes the implementation of excavations for the Makhoul Dam (Tilrace channel) above the level of (120) m, where the company was notified, according to the letter of the Ministry of Water Resources / Department of Planning and Follow-up No. (11968) on 5/11/2021, on the implementation of excavations on the right side of the dam, and it was started after preparing the site Work on 9/10/2021 after receiving the site
The above contract was signed on 12/30/2021 for an amount of (245,000,000) dinars, with an implementation period of (60) days.